Re: [Emerald] Mapp PC

Chris A. Christopher ( (no email) )
Tue, 04 Apr 2000 15:48:04 -0700

Would using the wrong MAPP PC type cause Emerald to not post accounts
correctly during a batch in process?

At 10:29 AM 04/04/2000 -0700, you wrote:
>"Chris A. Christopher" wrote:
>>
>> Hello,
>>
>> We are using MAPP PC for batching monthly CC's. Emerald is batching out an
>> Auth/AVS (code 9) instead of a Sale/AVS (code 10). This creates a two step
>> process of authorizing and then capturing the sale. Can, and how, would I
>> change the Emerald output to a code 10 instead of code 9? This will
>> eliminate one step.
>
>Use the "MAPP-PC V9.x" type rather than the original MAPP-PC
>type. Its about 1/2 down the list of types.
>
>
>--
>
>Dale E. Reed Jr. Emerald and RadiusNT
>__________________________________________
>IEA Software, Inc. www.iea-software.com
>
>For more information about this list (including removal) go to:
>http://www.iea-software.com/support/maillists/liststart
>
>